Workers with Great Lakes Construction Co. are preparing for the first concrete pour to repair a portion of the bridge deck ...
Crews allowed media onto the southbound portion of the Daniel Carter Beard Bridge for an up-close look at the repair project.
The Ohio Department of Transportation announced a major step in completing construction on the Daniel Carter Beard Bridge.
Saturday, crews began the first of two concrete pours on the deck of the Big Mac Bridge. Transportation officials say the first pour used a total 27 truckloads of concrete and the pour covered 250 ...
Construction workers are nearing a major milestone in the emergency repair works along the Daniel Carter Beard Bridge.
Prep work is underway for the next phase of the I-471 bridge project. The approach to the bridge was damaged beyond repair by ...
Three of seven steel girders to repair the highway connected to southbound Daniel Carter Beard are here. Four more are coming ...
ODOT is one step closer to reconstructing the Daniel Carter Beard Bridge after starting the first of two concrete pours.
Crews have installed additional massive steel girders as part of the ongoing repairs to the Daniel Carter Beard Bridge.
Officials told WCPO 9 News they will begin pouring concrete to form the deck on the southbound side of the bridge soon.
Local 12 was given the chance to take a tour of the section under repair of the Daniel Carter Beard bridge Friday morning.